| Today: |
— |
|
| Days remaining that we will accept shipment |
|
11/11/25 |
| Approx. days steel has been sitting on the supplier dock ready for pick up |
|
8/3/25 |
| Days since "expedited kit" should have been delivered |
|
7/15/25 |
| Days since first indication of significant supply chain failure |
|
5/20/25 |
| Days since latest acceptable contractual delivery date (1/11 email) |
|
9/11/25 |
| Days since revised late delivery date |
|
10/3/25 |
| Days since building permit issue |
|
6/18/25 |
| Days since assistance with production was offered |
|
5/25/25 |
| Days since first deposit was put down to "secure place in production" |
|
1/11/25 |